comment on this article

42 Technology completes six-month remote monitoring trial

42 Technology’s FuseOhm units have been installed into one of Western Power Distribution’s low voltage electricity substations as part of a six month field trial for the new low cost, network monitoring system.

42 Technology and Western Power Distribution have today announced the successful completion of the first UK field trials for FuseOhm.

FuseOhm is a form of remote monitoring and aims to allow all Distribution Network Operators (DNOs) to monitor the performance of every low voltage electricity substation.

The results demonstrate that FuseOhm is able to provide continuous real-time measurement and recording of critical parameters within substations – such as voltage, temperature and phase angle.

“FuseOhm is an easy retrofit solution that could provide network operators with low-cost monitoring at scale, and much better visibility of where to deploy smart management systems or specific network reinforcements.The FuseOhm units were installed, operating and collecting real-time data within one of our substations literally within minutes but the system could just as easily be included as an optional extra as part of all new installations at marginal extra cost,” said Ricky Duke, innovation and low carbon network engineer at Western Power Distribution.

Although several monitoring systems are already available, DNOs report that they can take two hours or more to install and are usually too expensive for routine and widespread use. As a result, current technologies tend only to be installed and used for short periods to help with fault diagnosis on a specific leg of the network when a customer reports a problem.

FuseOhm has been specifically designed to address this and to provide DNOs with a low-cost approach that could be rolled out to every substation.

These latest trial results follow on from a series of in-depth tests on pre-production prototypes carried out at The University of Strathclyde’s Power Networks Demonstration Centre in Glasgow (PNDC) where FuseOhm was shown to be robust and accurate over multiple tests, temperatures and environmental conditions.

Above: the FuseOhm display unit shows [from left to right] the actual current level for each of three fuseways, the peak current achieved within a pre-determined time period, as well as instantaneous phase voltage and temperature. The data can then be stored locally or transferred via a wired or wireless communications network for remote monitoring applications.

Author
Charlotte Hathway

Comment on this article


This material is protected by MA Business copyright See Terms and Conditions. One-off usage is permitted but bulk copying is not. For multiple copies contact the sales team.

What you think about this article:


Add your comments

Name
 
Email
 
Comments
 

Your comments/feedback may be edited prior to publishing. Not all entries will be published.
Please view our Terms and Conditions before leaving a comment.

Related Articles